     1= Code Camp IX Planning = 
     2 
     3== Dates == 
     4The eighth !SasView Code Camp will held in Grenoble, France starting March 25th 2019. 
     5 
     6== Travel and Accommodation == 
     7 
     8=== Hotel Suggestion === 
     9Stay tuned 
     10 
     11=== Getting to the Presqu'île === 
     12 
     13 
     14== Contact Information == 
     15 * Miguel Gonzales (phone +45 25 50 39 18) 
     16 
     17== Participants (current list) == 
     18||= Participant =|| Affiliation || Arrival || Departure || Hotel || Notes || 
     19|| Paul Butler || NIST || 2019-03-23 || 2019-04-03 ||  || current plan - not reserved || 
     20||  ||  ||  ||  ||  ||  || 
     21||  ||  || || || || || 
     22 
     23== Meals == 
     24=== Lunch === 
     25Coffee and cookies will be available either in the rooms or in the hallways. There is an onsite canteen which is probably the  
     26 
     27=== Dinner === 
     28If we want to eat together in town in the evenings then many places will need a booking for the number we have. Suggestions will be added here in due time 
     29 
     30== Proposed !Workgroups/Worktopics == 
     31The following are initial proposed work areas. The participants are a suggestion and you should look at the work and decided where your talents are best employed. 
     32 
     33||= Topic =||= Owner =||= Participants =||= Relevant Tickets etc =|| 
     34|| Sasview 5.0 / QtGUI || Piotr || Piotr || || 
     35|| Beta Approximation || Yun || Yun, Richard || [http://trac.sasview.org/query?status=accepted&status=assigned&status=new&status=reopened&workpackage=Beta+Approximation+Project&group=workpackage&col=id&col=summary&col=status&col=type&col=priority&col=milestone&report=12&order=milestone Beta Approximation Project Tickets] || 
     36|| Tutorials & Documentation || Steve || Steve, Paul B. || [http://trac.sasview.org/query?status=accepted&status=assigned&status=new&status=reopened&workpackage=SasView+Documentation&group=workpackage&col=id&col=summary&col=status&col=type&col=priority&col=milestone&report=12&order=milestone Documentation Tickets] || 
     37|| !Admin/Management/Planning || Paul || Paul, Andrew, Steve || [http://trac.sasview.org/query?status=accepted&status=assigned&status=new&status=reopened&workpackage=SasView+Admin&group=workpackage&col=id&col=summary&col=status&col=type&col=priority&col=milestone&report=12&order=milestone Admin Tickets] || 
     38|| 4.3 release || Paul B. || Paul B. ||  || 
     39|| Paper || Paul || Paul, Mathieu, Andrew, Steve, Richard etc etc || || 
     40 
     41== Developer Tools Links == 
     42 
     43JIRA : [https://jira.esss.lu.se/secure/RapidBoard.jspa?rapidView=617&projectKey=SASVIEW Kanban Board for SasGUI work] 
     44 
     45Jenkins : https://jenkins.esss.dk/sasview-beta/ 
     46 
     47Conda setup : http://trac.sasview.org/wiki/CondaDevSetup5.0 
     48 
     49== Agenda (tentative) == 
     50{{{#!td colspan=2 align=center 
     51=== Monday March 25th === 
     52}}} 
     53|- 
     54{{{#!td 
     55* 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     56* 9:15 Introduction to the site and computer setup 
     57}}} 
     58{{{#!td 
     59* TBA 
     60}}} 
     61|- 
     62{{{#!td colspan=2 align=center 
     63=== Tuesday March 26th === 
     64}}} 
     65|- 
     66{{{#!td 
     67 * 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     68}}} 
     69{{{#!td 
     70* TBA 
     71}}} 
     72|- 
     73{{{#!td colspan=2 align=center 
     74=== Wednesday March 27th === 
     75}}} 
     76|- 
     77{{{#!td 
     78 * 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     79}}} 
     80{{{#!td 
     81* TBA 
     82}}} 
     83|- 
     84{{{#!td colspan=2 align=center 
     85=== Thursday March 28th === 
     86}}} 
     87|- 
     88{{{#!td 
     89 * 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     90}}} 
     91{{{#!td 
     92* TBA 
     93}}} 
     94|- 
     95{{{#!td colspan=2 align=center 
     96=== Friday March 29th === 
     97}}} 
     98|- 
     99{{{#!td 
     100 * 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     101}}} 
     102{{{#!td 
     103* TBA 
     104}}} 
     105|- 
     106{{{#!td colspan=2 align=center 
     107=== Saturday March 30th === 
     108}}} 
     109|- 
     110{{{#!td colspan=2 
     111 * 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     112}}} 
     113|- 
     114{{{#!td colspan=2 align=center 
     115=== Sunday March 31st === 
     116}}} 
     117|- 
     118{{{#!td colspan=2 
     119 * 9:00 Arrival at ESRF/ILL site (Room/building assignment TBA) 
     120}}} 
     121 
     122 
     123== photos == 
     124