= Work Plan for Code Camp VI = The primary work plan consists of the tickets that the team have [#TicketsMarkedCriticalorBlockerforRelease4.2 marked as blocker or critical for release] and [#SESANSIntegrationTickets SESANS sub-project tasks]. Also by start of code camp (and during the camp) some bugs in 4.1.0 were identified which can and should be fixed for a patch release 4.1.1. This patch release should come out shortly after the code camp. Once all the [#TicketsMarkedforRelease4.1.1 4.1.1 tickets] and [#TicketsMarkedCriticalorBlockerforRelease4.2 critical/blocker tickets] have been addressed, [#OtherTicketsforRelease4.2 other issues] can be looked at. As tickets are closed or updated during the Code Camp they will appear on the [wiki:CodeCampVI/Planning/WorkDone work done list]. == Tickets Marked for Release 4.1.1 == [[TicketQuery(status!=closed&milestone=SasView 4.1.1,format=table,order=priority,col=summary|owner|reporter|workpackage)]] == Tickets Marked Critical or Blocker for Release 4.2 == [[TicketQuery(priority=blocker|critical&status!=closed&milestone=SasView 4.2.0,format=table,order=priority,col=summary|owner|reporter|workpackage)]] == SESANS Integration Tickets Progress: == Progress: [[SESANS Analysis]] [[TicketQuery(workpackage=SESANS Integration,format=table,order=priority,col=summary|owner|reporter|workpackage)]] == Other Tickets for Release 4.2 == [[TicketQuery(priority!=blocker|critical&status!=closed&milestone=SasView 4.2.0,format=table,order=priority,col=summary|owner|reporter|workpackage)]]